Stage 1 (Completed 4 July 2011)
- January 2009 – July 2009 – Schematic design
- February 2009 – Forward Brianese Architects engaged.
- October 2009 – Design development completed.
- 5 October 2009 – Parliamentary Standing Committee for public works approval.
- November 2009 – January 2010 – Early works tender period.
- January 2010 – Early building works tender approved and contractor (Hazell Bros) selected.
- 10 February 2010 – Early building works commenced.
- 3 March 2010 – Main building works tender closed.
- Mid March 2010 – Early building works completed.
- May 2010 – Main builder appointed. (VOS Construction)
- June 2010 – Main building works commence.
- June 2010 – 4 July 2011 - Stage 1 construction
Stage 2 (Scheduled for completion April 2012)
- July 2011 - April 2012 - Stage 2 construction